Full Bathroom Remodeling in University Park, TX: What It Costs and How Long It Takes
A full bathroom remodeling in University Park typically runs $9,000 – $28,000 and takes four to seven weeks of build time once demo starts. That range covers a complete gut of the room: new tile, vanity, shower or tub, toilet, lighting, ventilation, and finished plumbing and electrical. On the 1920s – 1950s brick cottages in ZIP 75225, the number lands mid-to-high in that range because original cast-iron plumbing and knob-and-tube-era wiring usually get corrected while the walls are open. Call (844) 797-4808 for a free on-site estimate and a written line-item quote.
The Sequence We Follow, Day by Day and Stage by Stage
A full bath gut follows a fixed order. Skipping a stage is how remodels end up reopening finished walls six weeks later. Here is the real sequence.
Stage 1: Site protection and demolition (2 – 3 days)
We seal the doorways and floor paths first, because dust travels through the whole house. Demo removes the old tile, vanity, toilet, tub or shower surround, and drywall back to studs where it’s wet or failing. You decide at this point whether to keep the existing layout or move a fixture, since that call changes everything downstream.
Stage 2: Rough-in corrections and framing (2 – 4 days)
Plumbing supply and drain lines get replaced or re-routed, along with electrical for lighting, GFCI protection, and the exhaust fan. If your University Park home still has cast-iron drains or old wiring, we replace that here, not later. You approve the fixture locations and the venting plan before anything closes up.
Stage 3: Rough inspection (1 day, plus city scheduling time)
The city inspects plumbing and electrical before drywall goes on. We schedule the inspection and meet the inspector; you don’t have to be home. This is the stage where University Park’s permitting process becomes real, and where we build in the wait.
Stage 4: Drywall, waterproofing, and tile (7 – 10 days)
Drywall, then cement backer board and a bonded waterproofing membrane in the wet areas, then tile. Laying tile on green board is the shortcut that leads to a failed shower pan later. You choose tile size, grout type, and niche placement before this stage so the schedule doesn’t stall.
Stage 5: Set, trim, and final inspection (5 – 7 days)
Vanity, countertop, toilet, shower glass, fixtures, mirror, and paint go in, then the final inspection. After that comes a punch walk with you. Our technicians have up to 12 years of experience, and they close out the job the same way they opened it: with the details checked and signed off.
Styles & brands we work with
- Kitchen remodeling
- Bathroom remodeling
- Home additions & ADU
- Roofing
- Windows & doors
- Driveway & pavers
- Fence
The Options You’ll Actually Choose Between
Most of the dollar swing on a full bath comes from four decisions you make before demo. Here’s the honest trade-off on each.
- Tile material: Porcelain runs roughly $4 – $12 per square foot installed and holds up against North Texas hard water with minimal upkeep. Natural stone costs two to three times more and needs sealing.
- Shower vs. tub: A tiled shower with a built-in bench is the most requested upgrade, but it’s a separate discussion from the tub-to-shower reconfiguration some homeowners need. Toilet brands for the room run from American Standard at the accessible end to Moen-compatible contemporary styles at the higher end.
- Vanity and countertop: A stock vanity with an integrated top lands at the low end of our $800 – $3,000 vanity range; a custom cabinet with a quartz top lands high. The gap is real, so decide before demo, not after.
- Ventilation: A properly sized exhaust fan tied to a timer is non-negotiable in humid North Texas summers. Cheap fans fail the inspection and fog the mirrors.
- Waterproofing method: A bonded membrane system costs more up front than cement board alone, but it’s what keeps a shower pan from leaking into the floor joists years down the road.
We carry a curated set of brand partners across every trade, from Kohler fixtures to tile and cabinetry lines, so you’re choosing on quality rather than whatever happens to be in stock. If this bath is part of a full Bathroom Remodeling in University Park scope that touches a second bath or a laundry room, tell us at the estimate so the plumbing work is priced once, not twice.
What Full Bathroom Remodeling Costs in University Park, TX
Our full bathroom remodeling range for University Park is $9,000 – $28,000. Where a specific job falls inside that band comes down to five variables:
- Room size: A 5-by-8 hall bath and a 10-by-12 primary bath are different jobs by roughly 50%.
- Existing condition: Cast-iron drains, galvanized supply lines, and failing subfloor are common in ZIP 75225 homes and push a job toward the top of the range.
- Layout changes: Moving a toilet or shower drain adds $1,500 – $4,000 in plumbing and framing.
- Material grade: Tile, vanity, and fixtures drive most of the visible spend; upgrade all three and you’ll land high.
- Permit and inspection scope: Plumbing and electrical changes require permits and inspections; a cosmetic refresh with no moves may not.
A written estimate from us lists each line with material allowance and labor, plus what’s excluded. What’s typically not included: hidden rot or foundation correction behind the wall, hazardous-material abatement, and any structural work if the inspector flags something once walls are open. We don’t promise to absorb those; we do flag them in writing and get your approval before doing them. Upfront pricing means the number you see is the number you pay, with no change orders for work already agreed to.
See the difference
Before
After
Before
After
Before
AfterWhat University Park Homes Specifically Do to This Job
University Park is a built-out, landlocked Park Cities enclave with essentially no vacant land, so nearly every full bathroom remodeling project here is a rebuild or major remodel inside a house that’s already standing. Housing stock runs from 1920s – 1950s brick and frame cottages to large new custom builds, often on 50- to 70-foot lots. On the older homes we routinely find pier-and-beam or early slab foundations, original cast-iron plumbing, and knob-and-tube-era wiring that get corrected during the renovation. Because lots are narrow and alleys back many blocks, staging and delivery access are tight, and mature live oaks have to be protected during demo haul-off. The permitting process and building department review are thorough, so we plan for the inspection schedule early. North Texas heat, expansive black clay, and heavy spring storms also mean we watch foundation and drainage around the bath, especially on homes near Snyder Plaza or along University Boulevard, where grading and older foundations compound the work.
Homeowners often pair the bath with exterior work at the same time; if you’re already staging a dumpster, look at our Roof Repair in University Park and Roof Replacement & Installation in University Park services to bundle the access and save the second setup.
Serving University Park, TX – Our Local Coverage Area
We serve University Park and nearby communities. Use the map below to see the area we cover. If you’re nearby, we can almost certainly help.
Frequently Asked – Full Bathroom Remodeling in University Park
Plan for four to seven weeks of build time once demo starts. Permitting and inspection scheduling add one to three weeks before that. The biggest schedule variable is whether plumbing or electrical has to be re-routed, which is common in older University Park homes. Call (844) 797-4808 for a realistic timeline on your specific room.
Yes, if the work touches plumbing, electrical, or structural elements, which full baths almost always do. A cosmetic refresh with no moves may not require one. We pull the permits and meet the inspections; you don’t have to coordinate with the city. Call (844) 797-4808 to confirm what your project needs.
Yes, and it’s often the smartest budget call. Keeping the toilet and drain in place and re-tiling around the existing rough-in avoids the $1,500 – $4,000 plumbing and framing premium. The trade-off is that layout stays the same. Call (844) 797-4808 to talk through whether keeping the layout works for your room.
Expect $9,000 – $28,000 for a full gut, with older ZIP 75225 homes typically landing mid-to-high in that band due to plumbing and wiring corrections. Material grade and layout changes are the two biggest levers. Call (844) 797-4808 for a written line-item quote; the estimate is free.
Every project is covered by our 730-Day Done Right Promise: if it’s not done right, we make it right. That’s one of the longest workmanship guarantees in the residential construction space. The written warranty travels with the job and is part of the final walkthrough. Call (844) 797-4808 with any warranty questions.
Get a Free Estimate for Full Bathroom Remodeling in University Park
Call (844) 797-4808 to schedule a free on-site estimate and design consult for full bathroom remodeling in University Park. A live person answers 24/7, and we’ll walk your room, measure, and talk through layout and material options before writing a line-item quote. You’ll also hear about the $1,000 off projects over $10,000 and 0% financing for 18 months. We cover University Park from our University Park service area, and you can read more about our Bathroom Remodeling service before your appointment.