Full Kitchen Remodeling in Carrollton, TX: What the Job Actually Takes
Full kitchen remodeling in Carrollton runs $14,000 to $45,000 and takes six to ten weeks of construction once permits clear. Every wall, cabinet, and fixture comes out and the room is rebuilt to current code. If you’re pricing one of these for a 1970s ranch off Josey Lane or a PUD in 75007, call (844) 797-4808 for a free on-site estimate. We’ll walk the room, check what’s behind the drywall, and write a line-item quote before you commit to anything.
How We Run a Full Kitchen Remodeling Job, Stage by Stage
You’ll know the schedule before demo starts. Here’s the real sequence, with the decisions you make and when.
Stage 1 – Design, selections, and permit (Weeks 1-4)
We measure the room, check the panel, and open a wall or two where it’s safe to confirm what the house has. You pick layout, door style, finish, countertop slab, and sink configuration. This is also when you test your community rules: if your neighborhood sits under an HOA with an architectural review committee, get the ARB packet in hand now, not on install day. We submit plans to the City of Carrollton and wait for the permit. In the older subdivisions, plan review often adds days because of original wiring and plumbing.
Stage 2 – Protection and demo (Days 1-4)
Day one is masking, floor cover, dust barriers, and shutting off the water. demo comes out fast: cabinets, counters, old tile, and usually the original 1970s soffit. Demo is also the first honest look at what’s behind the walls. This is where we find aluminum branch wiring or polybutylene supply lines, and you decide whether to replace them now or risk failing inspection later.
Stage 3 – Rough-in trades (Days 5-15)
Plumbing, electrical, and HVAC move first, then the rough inspection. If we’re relocating the sink or range, this is when the new lines go in. You confirm outlet and switch placement here, plus under-cabinet lighting runs and any dedicated circuits for a new range or dishwasher. Walls close after the inspector signs off, never before.
Stage 4 – Drywall, cabinets, and finishes (Days 16-40)
Drywall, texture, and paint, then cabinet set, countertop template, backsplash, and flooring. Countertop lead time is the long pole on most jobs: quartz or granite fabricators run two to three weeks from template to install. You approve the slab and edge profile before the template happens. Appliances land near the end so nothing gets damaged in the traffic path.
Stage 5 – Final inspection and punch list (Days 41-50)
The city does the final inspection, we walk the room with you, and you sign off item by item. The 730-Day Done Right Promise starts at that walkthrough, and it covers workmanship for two full years.
Styles & brands we work with
- Kitchen remodeling
- Bathroom remodeling
- Home additions & ADU
- Roofing
- Windows & doors
- Driveway & pavers
- Fence
The Options You’ll Choose Between (and What Each One Costs You)
- Stock vs. semi-custom cabinetry. Stock boxes in standard sizes save money and arrive faster; semi-custom from KraftMaid lets you hit odd wall lengths and a specific door style. On a full rebuild, semi-custom usually pays for itself in fewer filler panels and better storage.
- Quartz vs. granite vs. laminate. Quartz holds up to daily wear and doesn’t need sealing; Cambria is a solid pick if you want consistent veining. Granite costs similar and handles heat better. Laminate lands at the bottom of the $2,000-$6,500 countertop range but shows wear faster in a busy kitchen.
- Luxury vinyl plank vs. tile vs. hardwood. LVP handles the North Texas climate swings, spills, and pets at the lowest cost. Porcelain tile runs cooler and lasts longer but is harder on your feet at the sink. Hardwood matches a 1980s home’s original floors but needs recoating every several years.
- Layout changes. Keeping the sink, range, and fridge where they sit saves $3,000 to $8,000 in plumbing and electrical moves. Opening a wall to the living room adds light and needs a structural check; moving the sink to the island triples the plumbing rough-in line.
- Ventilation and lighting. A properly ducted range hood beats a recirculating unit every time in a kitchen that actually cooks. Recessed LED and under-cabinet strips are cheap to add during rough-in and expensive to retrofit later.
What Full Kitchen Remodeling Costs in Carrollton, TX
The lead range is $14,000 to $45,000. A tight galley rebuild with stock cabinets and laminate sits near the bottom. A gut remodel that moves plumbing, opens a wall, and uses semi-custom cabinets with quartz lands near the top.
| Line item | Typical range |
|---|---|
| Full kitchen remodel, all-in | $14,000-$45,000 |
| Cabinet installation | $4,000-$13,000 |
| Countertop installation | $2,000-$6,500 |
| Backsplash installation | $800-$2,500 |
| Kitchen island installation | $3,000-$10,000 |
Four variables push a job to the low or high end. Room size and layout: a 10×10 galley runs about half the cost of a 15×20 with an island. Condition behind the walls: original aluminum wiring or polybutylene in a 1970s house adds a whole-home electrical or plumbing upgrade before anything passes. Material grade: the spread between stock and semi-custom, laminate and quartz, is thousands of dollars on the same footprint. Permit scope: moving plumbing or structure means more drawings, more inspections, and more line items.
A written estimate covers cabinetry, counters, install labor, permits, demo, haul-away, and finish work. It usually doesn’t cover appliance costs, foundation repair if we find movement, or a full panel replacement if the electrical upgrade runs past the kitchen. We itemize that line separately so there’s no surprise later. Upfront pricing means the number you see is the number you pay on the scope we agreed on.
See the difference
Before
After
Before
After
Before
AfterWhat Carrollton Homes Specifically Do to This Job
A kitchen remodel in the older Carrollton subdivisions around 75006 and 75007 is rarely just a kitchen. Lot values there now exceed the aging ranch homes sitting on them, so owners rebuild rather than move, and the work becomes permitting-driven reconstruction. In these neighborhoods off Josey Lane and Belt Line Road, we routinely pull cabinets and find original 1970s aluminum branch wiring and polybutylene supply lines. Both have to be fully replaced before the job will pass inspection, which turns a routine kitchen into a whole-house electrical or plumbing upgrade. Add the expansive clay soils: if the slab has cracked, the floor goes down wrong until the foundation is addressed, so we check before template. Summer hail and freeze events like 2021 also show up, usually as pipe-burst damage that needs fixing before the rebuild. On top of all that, mature deed restrictions in the area’s PUDs and HOAs mean a door style or exterior change may need ARB approval, so we confirm the approved palette before the order goes in. We cover all four ZIPs (75007, 75006, 75011, 75010) as part of our wider Carrollton service, and this room is one piece of the broader Kitchen Remodeling in Carrollton work we handle.
Serving Carrollton, TX – Our Local Coverage Area
We serve Carrollton and nearby communities. Use the map below to see the area we cover. If you’re nearby, we can almost certainly help.
Frequently Asked – Full Kitchen Remodeling in Carrollton
Plan on six to ten weeks of construction after permits clear, plus three to four weeks of design and permit review up front. Older homes that need wiring or plumbing upgrades run toward the high end.
Call (844) 797-4808 and we’ll give you a schedule for your address.
Yes. Any work that touches plumbing, electrical, or structure needs a City of Carrollton permit and inspection. We pull the permits and hold the inspections; you never deal with the city yourself.
Call (844) 797-4808 to talk through the permit scope for your job.
Yes, and it’s the single biggest lever on cost. Keeping the sink, range, and fridge in place can save $3,000 to $8,000. A new island or wall opening still works if the plumbing and load paths allow it, and we’ll tell you honestly when they don’t.
Call (844) 797-4808 for a free walkthrough on what your layout allows.
The range is $14,000 to $45,000, with the number driven by room size, what’s behind the walls, material grade, and permit scope. Every figure we quote is line-item and fixed for the scope we agree on.
Call (844) 797-4808 for an exact quote – estimates are free.
Every project is backed by the 730-Day Done Right Promise: if it’s not done right, we make it right, for two full years. That covers workmanship, and it’s in writing.
Call (844) 797-4808 to hear how it works on your project.
Get a Free Estimate for Full Kitchen Remodeling in Carrollton
Call (844) 797-4808 and a live person picks up, day or night. We’ll schedule a free on-site estimate, walk the kitchen, and check what’s behind the walls and under the floor. You’ll get a written, line-item quote with no change-order games, and you can ask about 0% financing for 18 months or the $1,000 off projects over $10,000. If you’re pairing the kitchen with a bath, homeowners often add Full Bathroom Remodeling in Carrollton or Walk-In Showers & Shower Remodeling in Carrollton in the same pass. Our kitchen remodeling service uses trusted brands like KraftMaid and Cambria. Call today to start.