Full Kitchen Remodeling in Addison, TX: What It Involves and What It Costs
Full kitchen remodeling in Addison runs $14,000 to $45,000 for most jobs, and a typical project takes six to ten weeks once permits clear. You get a complete tear-out and rebuild: cabinets, counters, backsplash, flooring, lighting, sink and faucet, ventilation, and the finish carpentry that ties it together. The kitchen usually sits in a 1970s or 1980s unit where the layout was built around old appliance sizes, so expect to make several build-decisions early. Call (844) 797-4808 and we’ll walk you through the scope on your specific kitchen before you commit to anything.
How Full Kitchen Remodeling Actually Runs, Stage by Stage
Most of what makes a kitchen remodel smooth or miserable is sequencing. Here’s the real order we work in, and where you’ll be asked to decide.
Stage 1: Site protection and demolition (days 1 – 3)
Day one is floor protection, dust barriers at the doorways, and shutting off the feeds. Demolition pulls the old cabinets, counters, and flooring back to the studs and subfloor. You’ll want a temporary kitchen plan in place before we start, because this stretch is the messiest and the most disruptive.
Stage 2: Rough-in trades and inspection (days 4 – 10)
Plumbing, electrical, and any HVAC or venting changes go in now. If a wall or header is moving, that happens here too. In Addison, this is where a town inspector signs off before anything gets covered back up. Once the rough-in passes, the walls close.
Stage 3: Drywall, primer, and finished surfaces (days 11 – 22)
Walls get patched and primed, the ceiling texture matched, and the finish ceiling and trim surfaces go on. This is where the room starts feeling real. Your cabinet order should already be on site or in transit by now, since cabinet lead times are usually the long pole.
Stage 4: Cabinets, countertops, and the templating gap (days 23 – 38)
Base and wall cabinets set first, then countertops get templated. There’s a real gap between template and install for stone, often one to two weeks, so plan for a pause here. We schedule the appliance delivery and the sink and faucet around that window.
Stage 5: Backsplash, flooring, trim, and final inspection (days 39 – 56)
Tile work, the final flooring run, lighting and switch trim, and the last plumbing hookups finish the job. We call for the final inspection, then walk the room with you item by item so nothing gets quietly skipped.
Styles & brands we work with
- Kitchen remodeling
- Bathroom remodeling
- Home additions & ADU
- Roofing
- Windows & doors
- Driveway & pavers
- Fence
The Options You’ll Be Choosing Between
Full kitchen remodeling forces a set of choices most homeowners haven’t priced before. Here’s the honest trade-off on each.
- Cabinets: semi-custom (usually the sweet spot here, plenty of finish and size flexibility), full-custom for irregular layouts and tight clearances, or stock for the budget end. Cabinet boxes and drawer slides decide how the room feels in five years far more than the door style.
- Countertops: quartz is durable and low-maintenance and works in every kitchen; natural stone (granite, marble) has more character but needs sealing and can stain; laminate costs less but shows wear. The edge profile and the seam placement are what most people notice, not the slab.
- Backsplash: ceramic and porcelain tile, glass, or a full-height slab. A slab makes a strong single visual and costs more; tile gives you more pattern freedom at a lower line item.
- Flooring: luxury vinyl plank (best cost-to-durability for a kitchen), porcelain tile (holds up to spills and heat), or engineered hardwood (warmer underfoot, needs more care near the sink and dishwasher).
- Lighting and ventilation: recessed cans plus under-cabinet task lighting, and a properly sized range hood vented to the outside. In a North Texas kitchen, good hood venting matters more than most people expect when the house gets sealed up tight for summer AC.
- Appliances: induction vs gas range depends on whether you want new gas plumbing run; panel-ready or standard finishes change the cabinet budget.
What Full Kitchen Remodeling Costs in Addison, TX
The working range for a full kitchen remodel in Addison is $14,000 to $45,000. A smaller-unit kitchen with stock cabinets and laminate tops can land near the bottom. A larger unit with custom cabinetry, stone counters, relocated plumbing, and upgraded appliances lands near the top.
What pushes a job toward either end:
- Size and layout: more linear feet of cabinetry and counter directly raises the material line.
- Existing condition: old wiring, water damage, or a soffit that has to come down reveals work that wasn’t in the original scope.
- Relocating plumbing or electrical: moving a sink or range away from existing feeds adds real money. Keeping them put is the single biggest cost saver.
- Material grade: the gap between stock and custom cabinets can be tens of thousands of dollars on the same footprint.
- Permit scope: more trade work means more inspection steps and a longer schedule.
Your written estimate should show line items for demo, rough-in trades, cabinets, counters, tile, flooring, and finish carpentry, with allowances spelled out so the number holds. Requests that show up after work starts are change orders, and those are real dollars. No-hassle upfront pricing is the rule here: the number you see is the number you pay unless the scope genuinely changes.
See the difference
Before
After
Before
After
Before
AfterWhat Addison Homes Specifically Do to This Job
Addison is a built-out commercial and multifamily enclave, ZIP 75001, where ground-up residential construction is rare. Steep yourself in that reality and nothing about a kitchen remodel here surprises you. Most of the kitchens we see are inside apartment communities and low- or mid-rise buildings from the 1970s and 1980s, not traditional single-family houses. That changes the work.
For one thing, the building department is the Town of Addison’s, and interior renovation requires permits and inspections. Work gets squeezed onto tight, shared-parking sites along Belt Line Road and Addison Road, and staging a dumpster and materials without shutting down the building’s parking or a neighbor’s afternoon takes planning. Kitchens in mid-rise buildings also sit above or beside other units, so water shutoffs, noise windows, and elevator access all get scheduled, not assumed.
The other local reality is climate. North Texas summers push 100°F+, so we keep the same jobsite doors closed and the AC running to protect cabinets and flooring from heat and humidity swings, and we plan the envelope details to handle the occasional freeze event. Tight clearances in these older kitchens often mean cabinet dimensions and appliance sizes come off real field measurements, not a catalog. If the remodel touches a shared wall or a load point, we put it in writing before anybody swings a hammer.
Serving Addison, TX – Our Local Coverage Area
We serve Addison and nearby communities. Use the map below to see the area we cover. If you’re nearby, we can almost certainly help.
Frequently Asked: Full Kitchen Remodeling in Addison
Plan on six to ten weeks from permit approval, and the schedule hinges on cabinet lead times and the stone templating gap. Jobs that keep plumbing and structure in place stay closer to the short end. Call (844) 797-4808 for a schedule estimate on your specific kitchen.
Yes. The Town of Addison building department requires permits for interior renovation work, and inspections happen at the rough-in stage and again at final. We handle the permit pull and schedule the inspections. If you’re not ready and want to see the full scope, start with our Kitchen Remodeling in Addison page.
Yes, and it’s the most common and most cost-effective path. Keeping the sink, range, and existing walls where they are avoids relocation costs and extra trade work. Bring in our Kitchen Remodeling service if you’re weighing a smaller partial update instead of a full tear-out.
Cabinet grade, counter selection, and whether plumbing or electrical relocates. The $14,000 to $45,000 range in Addison is wide because those three choices drive most of it. We put every line in writing so you see exactly where your dollars go. Call (844) 797-4808 for an exact quote, estimates are free.
Every job is covered by the 730-Day Done Right Promise, one of the longest workmanship guarantees in the residential construction space. If something isn’t done right, we make it right. If a job touches more than the kitchen, homeowners often pair this with Full Bathroom Remodeling in Addison, and we cover Addison end to end. We also handle Walk-In Showers & Shower Remodeling in Addison for the same units.
Get a Free Full Kitchen Remodeling Estimate in Addison
Planning a full kitchen remodel in Addison? Call (844) 797-4808 and we’ll set up a free on-site estimate and design consult. We measure the room, walk through the scope, and hand you an upfront, line-item price with no surprises. A live person answers around the clock, and most calls take about ten minutes to schedule. Our technicians have up to 12 years of experience, and every crew arrives background-checked and in uniform. From foundation to finish line, it’s built to last and backed in writing.