New Detached ADU in Irving, TX: What You’re Actually Building
A new detached ADU in Irving typically runs $45,000 – $130,000 and takes four to seven months from permit submittal to final inspection. The structure sits on its own footprint, carries its own utilities, and needs its own address or unit designation before anyone can legally live in it. Call (844) 797-4808 and we’ll walk your lot and give you a real number.
How a New Detached ADU Comes Together, Stage by Stage
The sequence matters more than any single material choice, because Irving’s inspection calendar and clay soils both punish jobs that skip steps. Here’s what actually happens.
- Stage 1 – Site and soils (week 1 – 2): We walk the lot, check setbacks against what the city will allow, and pull a geotechnical read on the black clay. On South Irving lots in 75060 and 75061 this is where we find out whether the existing grade supports a post-tension slab or whether we’re drilling piers. You decide the footprint and orientation here; everything downstream depends on it.
- Stage 2 – Design and permit submittal (week 3 – 8): Plans go to the city with structural, plumbing, electrical and mechanical sheets. Irving’s plan review is the long pole. You sign off on the layout and exterior finish selections while this runs.
- Stage 3 – Foundation and framing (week 9 – 16): Forming, rebar or cable, pour, cure, then framing. Summer pours here get scheduled at dawn because afternoon heat will crack a slab. You’ll walk the framed shell with us before anything gets closed up.
- Stage 4 – Rough-ins and inspections (week 17 – 22): Electrical, plumbing and HVAC rough-in, then framing, mechanical and insulation inspections in sequence. Each one has to pass before the next trade starts.
- Stage 5 – Finishes and final (week 23 – 30): Drywall, cabinets, flooring, fixtures, exterior siding and paint, then the final inspection and utility connections. You get the walkthrough and the punch list closes in writing.
Decisions stack up front on purpose. Layout, exterior cladding and roof pitch get locked in Stage 2. Interior finishes get locked by Stage 3. Moving a wall after framing is open is cheap; moving it after drywall is not.
Styles & brands we work with
- Kitchen remodeling
- Bathroom remodeling
- Home additions & ADU
- Roofing
- Windows & doors
- Driveway & pavers
- Fence
The Choices That Shape the Build
Most of the money sits in five decisions, and each one has a real trade-off.
- Foundation type: Post-tension slab is the default for a detached ADU on stable grade. Drilled piers add cost but are often mandatory on the older South Irving lots where the original house sits on shallow footings. Skimp here and you’ll pay for it in drywall cracks within three summers.
- Structure: Stick-framed wood is standard and flexible. Structural insulated panels go up faster and insulate better but cost more per square foot up front.
- Exterior cladding: Brick veneer matches the Irving street fabric and holds up for decades. Fiber cement siding is lighter on the budget and repaints cleanly. Both work; brick costs more and asks less of you later.
- Windows: This is where a low number and a high number diverge fast. A builder-grade unit meets code. Something from Andersen or an ES Windows line rated for North Texas heat gain will cost more and keep the interior cooler through August. We quote the actual product, not a category.
- Utilities: Trenching from the main house to a detached structure is a line item nobody expects. Distance from the meter drives it.
What a New Detached ADU Costs in Irving, TX
Budget $45,000 – $130,000 for the structure and its site work, with most Irving builds landing in the middle of that band once utilities, foundation and finishes are counted.
| Line Item | Typical Range |
|---|---|
| Site prep, grading, trenching | $4,000 – $12,000 |
| Foundation (slab or piers) | $8,000 – $22,000 |
| Shell, framing, roof, cladding | $18,000 – $55,000 |
| Electrical, plumbing, HVAC | $7,000 – $18,000 |
| Interior finishes | $8,000 – $23,000 |
What pushes a job to the bottom of the range: a flat, cleared lot close to the main meter, slab foundation, fiber cement exterior, modest fixtures. What pushes it up: piers, a long utility run, brick veneer, a full kitchen and bath package, and any impact-rated window spec.
A written estimate from us lists each trade line separately. What it won’t hide is the permit fee, which the city sets and we pass through at cost. What it excludes is landscaping restoration and any HOA design review fee. No change orders unless you ask for a change.
See the difference
Before
After
Before
After
Before
AfterWhat Irving Specifically Does to a Detached ADU Build
Irving splits into two construction markets along the SH-114 corridor, and a detached ADU lands differently on each side. On the older South and central lots in 75060 and 75061, you’re working postwar brick ranches on shallow footings, and the clay beneath them swells and shrinks with every wet-dry cycle. That’s why pier-and-beam or re-engineered post-tension work is a standard line item here before framing starts. Contractors from other metros miss it and get surprised at inspection.
Out toward Las Colinas and the 75038 and 75039 edge, the lots are tighter, the HOA rules are stricter, and the surrounding construction is commercial-grade. Setback and height review gets a harder look. Either way, plan review takes weeks, not days, and we schedule around the city’s inspection windows rather than promising a date we can’t hold.
Serving Irving, TX – Our Local Coverage Area
We serve Irving and nearby communities. Use the map below to see the area we cover. If you’re nearby, we can almost certainly help.
Frequently Asked: New Detached ADU in Irving
Four to seven months from permit submittal to final inspection, with the city’s plan review eating six to eight weeks of that. Construction itself runs about 20 weeks on a typical 600-square-foot unit. Call (844) 797-4808 for a timeline tied to your lot.
Yes. A new detached ADU requires full plan review and separate foundation, framing, electrical, plumbing and mechanical inspections. We pull the permits and schedule every inspection for you. Call (844) 797-4808 to start the conversation.
Not usually. A detached structure needs its own utility runs from the main house, and that means trenching regardless of layout. The variable is distance, not whether. Call (844) 797-4808 and we’ll measure the run on your lot.
$45,000 – $130,000, driven mostly by foundation type, utility distance and finish grade. Estimates are free and written line by line, so you see where your number comes from. Call (844) 797-4808.
Every project carries our 730-Day Done Right Promise: if it’s not done right, we make it right. That covers workmanship for two full years, well past the point where most builders have moved on. Call (844) 797-4808 with questions before you sign anything.
Homeowners often pair the ADU build with Backsplash, Tile & Flooring in Irving for the interior finishes, and some line up Kitchen Design & Layout in Irving if the unit gets a full kitchen. It’s part of a full Home Additions & ADU in Irving scope, and you can see the wider range of work on our Home Additions & ADU service page. We serve the whole of Irving and the surrounding area.
Get a Real Number on Your Irving ADU
Call (844) 797-4808 for a free on-site estimate on a new detached ADU in Irving. A live person answers, day or night. We’ll walk the lot, check setbacks, talk through foundation options and hand you a written line-item estimate: upfront pricing, no surprises. Projects over $10,000 get $1,000 off, and 0% financing for 18 months is available.